AI Concierge
Welcome to TaktFlow AI Concierge. I am your intelligent project assistant, powered by real-time data from all project services. I can analyze schedules, predict delays, run simulations, and provide actionable recommendations.
How can I help you today?
What's the current project status?
Here is the current status for Hotel Sapphire:
Overall Progress: 45% complete (on track)
Current Takt Period: T5 of 11
PPC: 93% (+5% from last week)
AI Health Score: 87/100
Active Trades:
Open Constraints: 3
Key Insight: The Structure trade is performing exceptionally well, creating buffer that partially offsets the MEP delay. If the MEP constraint is resolved by T7, the overall schedule will not be impacted.
Which trades are behind schedule?
Trades Behind Schedule Analysis
Based on current flowline data and takt plan comparison:
1. MEP Rough -- 1.5 days behind in Zone D
- Root cause: Material delivery delay (Constraint C1)
- Impact: Risk of stacking with Drywall in Zone E
- Mitigation: Expedite delivery + add overtime crew
2. Drywall -- 0.5 days behind in Zone C
- Root cause: Crew shortage (Constraint C2)
- Impact: Minor -- buffer absorbs the delay
- Mitigation: Reallocate from Structure (ahead of schedule)
Trades On or Ahead:
Recommendation: Focus on the MEP Rough delay. If not resolved by T7, it will cause trade stacking with Drywall in Zone E, reducing productivity by an estimated 15-20%.