Takt Editor
YA
Takt:
Buffer:
Periods18
Duration123d
Start16 Feb
End19 Jun
Trades7
Zones6
Stacking0
Buffer Health100%
TradeTaktBufCrew | Zone A Ground Floor | Zone B 1st Floor | Zone C 2nd Floor | Zone D 3rd Floor | Zone E 4th Floor | Zone F 5th Floor | |
|---|---|---|---|---|---|---|---|
Structure | Completed T1 16 Feb | Completed T2 23 Feb | Completed T3 2 Mar | Completed T4 9 Mar | Completed T5 16 Mar | Completed T6 23 Mar | |
MEP Rough | Completed T3 2 Mar | Completed T4 9 Mar | Completed T5 16 Mar | Completed T6 23 Mar | In Progress T7 30 Mar | In Progress T8 6 Apr | |
Drywall | Completed T5 16 Mar | Completed T6 23 Mar | In Progress T7 30 Mar | In Progress T8 6 Apr | Planned T9 13 Apr | Planned T10 20 Apr | |
MEP Finish | In Progress T7 30 Mar | In Progress T8 6 Apr | Planned T9 13 Apr | Planned T10 20 Apr | Planned T11 27 Apr | Planned T12 4 May | |
Flooring | Planned T9 13 Apr | Planned T10 20 Apr | Planned T11 27 Apr | Planned T12 4 May | Planned T13 11 May | Planned T14 18 May | |
Paint | Planned T11 27 Apr | Planned T12 4 May | Planned T13 11 May | Planned T14 18 May | Planned T15 25 May | Planned T16 1 Jun | |
Finishes | Planned T13 11 May | Planned T14 18 May | Planned T15 25 May | Planned T16 1 Jun | Planned T17 8 Jun | Planned T18 15 Jun |