Takt Editor

YA
Takt:
Buffer:
Periods18
Duration123d
Start16 Feb
End19 Jun
Trades7
Zones6
Stacking0
Buffer Health100%
TradeTaktBufCrew
Zone A
Ground Floor
Zone B
1st Floor
Zone C
2nd Floor
Zone D
3rd Floor
Zone E
4th Floor
Zone F
5th Floor
Structure
Completed
T1
16 Feb
Completed
T2
23 Feb
Completed
T3
2 Mar
Completed
T4
9 Mar
Completed
T5
16 Mar
Completed
T6
23 Mar
MEP Rough
Completed
T3
2 Mar
Completed
T4
9 Mar
Completed
T5
16 Mar
Completed
T6
23 Mar
In Progress
T7
30 Mar
In Progress
T8
6 Apr
Drywall
Completed
T5
16 Mar
Completed
T6
23 Mar
In Progress
T7
30 Mar
In Progress
T8
6 Apr
Planned
T9
13 Apr
Planned
T10
20 Apr
MEP Finish
In Progress
T7
30 Mar
In Progress
T8
6 Apr
Planned
T9
13 Apr
Planned
T10
20 Apr
Planned
T11
27 Apr
Planned
T12
4 May
Flooring
Planned
T9
13 Apr
Planned
T10
20 Apr
Planned
T11
27 Apr
Planned
T12
4 May
Planned
T13
11 May
Planned
T14
18 May
Paint
Planned
T11
27 Apr
Planned
T12
4 May
Planned
T13
11 May
Planned
T14
18 May
Planned
T15
25 May
Planned
T16
1 Jun
Finishes
Planned
T13
11 May
Planned
T14
18 May
Planned
T15
25 May
Planned
T16
1 Jun
Planned
T17
8 Jun
Planned
T18
15 Jun