Dashboard
YA
PPC
93%
โฒ 5% from last week
Takt Progress
T5
of 11 periods
Open Constraints
3
1 critical
AI Score
87
Project health index
AI Concierge
Online
Insight
Structure trade is 2 days ahead of schedule. Consider pulling MEP Rough forward to utilize the buffer.
Warning
MEP material delivery delay may impact Zone E by T8. Recommend early procurement action.
Recommendation
PPC trending upward for 3 consecutive weeks. Current team productivity is above benchmark.
Recent Activity
Structure completed Zone D โ 3rd Floor
2 hours agoNew constraint: MEP material delivery delayed
4 hours agoAI detected potential trade stacking in Zone E
5 hours agoMEP Rough completed Zone B โ 1st Floor
6 hours agoTakt Period T4 completed โ all trades on schedule
YesterdayOpen Constraints
MEP duct delivery delayed
criticalMEP Rough ยท Zone E
Drywall crew shortage
highDrywall ยท Zone D
RFI #042 โ ceiling detail revision
mediumFinishes ยท Zone C
Constraint Removal Rate78%
2
Active Projects
7
Total Trades
6
Takt Zones
78%
CRR